4. Examples of optimal order settings (1–10)

Created by Kamila Dorušáková, Modified on Fri, 20 Feb at 11:50 AM by Kamila Dorušáková

Below are typical and proven configurations for a standard CCI installation.


4.1 Flow: PV → Consumption / Accumulation

 

DeviceOrderJustification
Heating pump1

Direct consumption, high contribution

EV charger2

Flexible consumption

BESS (charging)3

Storage only after consumption

GRID (export)-

Only residual energy


4.2 Flow: Production / BESS → GRID (reserved power)


Equipment

Attenuation order

Justification

BESS (discharge)
1

Fastest regulation

PV

2

Restriction only after BESS

Scenario: drop in consumption → first, BESS discharge is reduced, then PV power.


4.3 Flow: GRID → Consumption / Accumulation (reserved power input, protection)


Equipment

Order

Justification

EV charger

1Most flexible consumption
Heating pump2Can be limited in the short term
BESS (charging)3Can be limited during overload

Other technologies 4-6 According to criticality


4.4 Summary of recommended priorities


Energy flow  
Priority 1
Priority 2
Priority 3
PV → consumption

Heating pump
EV charger
BESS Export to GRID
BESS



PV


GRID → consumption 
EV charger
Heating pump
BESS



Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article